Simetria upgraded 42 PBSA studios in Wembley within a five-week summer programme — integrating new kitchens, flooring, furniture and beds, electrical works and internal door upgrades under one integrated delivery programme.
Greystar Europe
2024
London
£303k
Contract Value
42
Units Delivered
42
Fire Doors
42
Furniture Items
5
Weeks Installation
Project Overview
42-STUDIO PBSA SUMMER REFURBISHMENT & COMPLETE INTERNAL UPGRADE
A fast-track PBSA summer refurbishment programme delivered across 42 student studios in Wembley, London. Simetria coordinated the complete upgrade of the accommodation, including new kitchens, flooring, furniture, beds and mattresses, electrical works and internal doors.
Delivered within a five-week summer window, the programme brought multiple refurbishment workstreams together under one coordinated delivery team, with all studios completed ready for student occupation.
What we delivered
42 PBSA STUDIOS FULLY REFURBISHED
01
Complete refurbishment of 42 student studios delivered within a restricted five-week summer programme, coordinating multiple trades and workstreams from strip-out through to final completion and handover.
42 NEW KITCHENS
02
Installation of new studio kitchens, providing a complete refresh of the principal living spaces with all works coordinated as part of the wider refurbishment programme
COMPLETE KITCHEN, FIRE DOORS, FURNITURE, ELECTRICAL & INTERNAL UPGRADES
03
New furniture packages, beds and mattresses installed across the studios alongside electrical works and internal door upgrades, providing fully finished rooms ready for incoming students.
£303k
Contract value
42
Units Delivered
42
Fire Doors
42
Furnitrure Items
5
Weeks Installation