120-Apartment PBSA Refurbishment, Nottingham
PBSA ROLLING REFURBISHMENT
Greystar Europe
2025
Nottingham
Project Overview
120-APARTMENT OCCUPIED PBSA REFURBISHMENT — 12 COMPLETED EVERY WEEK
Simetria delivered the in-house refurbishment of 120 student apartments in Nottingham while the PBSA remained occupied — completing 12 apartments every week through a fast-track rolling programme of flooring, decoration, furniture and M&E upgrades.
A fast-track rolling refurbishment programme across 120 student apartments within an occupied PBSA development in Nottingham. Simetria delivered the works entirely through its in-house team, completing 12 apartments every week while maintaining the operation of the wider building. The programme included new flooring, painting and decoration, beds and mattresses, electrical works, upgraded lighting and new heating, with each apartment progressed through a controlled rolling sequence from commencement to completion.
What we delivered
120 APARTMENTS REFURBISHED IN OCCUPATION
01
Complete refurbishment of 120 student apartments while the wider PBSA development remained operational, with works carefully sequenced to maintain resident access, minimise disruption and keep the programme moving continuously.
12 APARTMENTS COMPLETED EVERY WEEK
02
A tightly controlled fast-track rolling programme delivering 12 completed apartments each week. Simetria’s directly managed in-house team moved systematically through the building, providing consistent quality and predictable weekly handovers.
FLOORING, FURNITURE & M&E UPGRADES
03
New flooring, painting and decoration, beds and mattresses, electrical works, replacement lighting and heating upgrades delivered as an integrated package within each apartment before final completion and handover.