Full PBSA Studio Upgrades
Simetria upgraded 34 PBSA studios in Wembley within a five-week summer programme — integrating new kitchens, flooring, furniture and beds, electrical works and internal door upgrades under one integrated delivery programme.
Greystar Europe
2023
London
£245k
Contract Value
36
Units Delivered
36
Furniture Items
5
Weeks Installation
Project Overview
34 - STUDIO PBSA SUMMER REFURBISHMENT & COMPLETE INTERNAL UPGRADE
A fast-track PBSA summer refurbishment programme delivered across 34 student studios in Wembley, London. Simetria coordinated the complete upgrade of the accommodation, including new kitchens, flooring, furniture, beds and mattresses, electrical works and internal doors. Delivered within a five-week summer window, the programme brought multiple refurbishment workstreams together under one coordinated delivery team, with all studios completed ready for student occupation.
What we delivered
34 PBSA STUDIOS FULLY REFURBISHED
01
Complete refurbishment of 34 student studios delivered within a restricted five-week summer programme, coordinating multiple trades and workstreams from strip-out through to final completion and handover.
34 NEW KITCHENS
02
Installation of new studio kitchens, providing a complete refresh of the principal living spaces with all works coordinated as part of the wider refurbishment programme
COMPLETE KITCHEN, FURNITURE, ELECTRICAL & INTERNAL UPGRADES
03
New furniture packages, beds and mattresses installed across the studios alongside electrical works and internal door upgrades, providing fully finished rooms ready for incoming students.
£245k
Contract value
36
Units Delivered
36
Furnitrure Items
5
Weeks Installation
6
Team Size