Stockwell Fire Door Remediation Project

Fire Door Compliance

FIRE DOOR REMEDIATION | 333 FIRE DOORS

Simetria delivered fire door remediation works across 333 doors at this Stockwell residential development. Working within a live building environment, the programme combined structured assessment, planned remedial works and asset-level records as part of a coordinated 11-building fire door compliance programme.

The Stockwell project required a structured approach to delivering fire door compliance works across 333 individual door assets. The programme formed part of the client's wider 4,500 plus fire door portfolio and was coordinated to support efficient delivery within an occupied residential environment.

‍

This project combined meaningful scale with the practical demands of an occupied residential environment. Simetria's coordinated approach provided consistent remediation, controlled site delivery and traceable records across 333 doors while aligning with the standards used throughout the wider portfolio.

‍This project formed part of Simetria's wider fire door remediation programme across 11 residential buildings. Delivering the portfolio through one coordinated approach provided consistency in remediation methodology, quality assurance, reporting and accountability across more than 4,500 fire doors.

What we delivered

Structured Fire Door Survey

01

Door condition and defects were captured systematically against our BM TRADA 24 point checklist to create a clear schedule of required works across the building.

Planned Remediation

02

Works were sequenced to address identified defects efficiently while supporting continued operation of the occupied development.

Digital Golden Thread Records

03

Completed actions and supporting evidence were maintained against individual fire door assets for future reference and maintenance.

Deep insights on other projects we have delivered

Absolutely amazing dolor sit amet beyond compareAbsolutely amazing dolor sit

All Fire Door Compliance Projects

London

Refurbishment

Amenity Rooms Upgrade

BTR Rooftop & Resident Lounge Upgrade, London | Simetria

ROOFTOP

GARDEN

STUDY

LOUNGE

£65K

INVESTMENT

Electrical Work

Flooring

Furnishings

Furniture

Painting and Decoration

Southampon

Integrated Projects

Summer Refurbishment

9-Studio PBSA Summer Refurbishment, Southampton | Simetria

9

STUDIOS

4

WEEKS

£100K

INVESTMENT

Beds & Mattresses

Electrical Work

Ensuite & Bathroom Upgrade

Flooring

Furnishings

York

Integrated Projects

New Studio Conversion

Resident Lounge to PBSA Studio Conversion, York | Simetria

4

CONVERSIONS

6

WEEKS

£140K

INVESTMENT

Beds & Mattresses

Electrical Work

Ensuite & Bathroom Upgrade

Fire Doors

Flooring

York

Refurbishment

110 Ensuite RefurbIshment

110-Ensuite PBSA Refurbishment, York | Simetria

110

UNITS

20

WEEKS

£645K

INVESTMENT

Electrical Work

Ensuite & Bathroom Upgrade

Flooring

Internal Doors

Painting and Decoration

Nottingham

Refurbishment

120-Unit Rolling Refurb

120-Apartment PBSA Refurbishment, Nottingham | Simetria

120

UNITS

20

WEEKS

£160K

INVESTMENT

Beds & Mattresses

Electrical Work

Ensuite & Bathroom Upgrade

Flooring

Furnishings

London

Integrated Projects

Luxury Refurbishment

Luxury BTR Apartment Refurbishment & FF&E, London | Simetria

12

Apartments

5

Weeks

£350k

Investment

Electrical Work

Ensuite & Bathroom Upgrade

Flooring

Internal Doors

Kitchens

London

Integrated Projects

Luxury Refurbishment

12 Luxury BTR Apartments Refurbished, London | Simetria

£250k

Contract value

12

APARTMENTS

5

WEEKS

Electrical Work

Ensuite & Bathroom Upgrade

Flooring

Internal Doors

Kitchens

Brighton

Refurbishment

New Luxury Apartments

ROX Brighton: 68-Apartment Interiors & FF&E | Simetria

72

Apartments

36

Weeks

£1,000k

Investment

Electrical Work

Ensuite & Bathroom Upgrade

Flooring

Furnishings

Furniture

Liverpool

Integrated Projects

Summer Refurbishments

Liverpool PBSA Refurbishment & 250 Fire Doors | Simetria

125

Unis

250

Fire Doors

£752k

Investment

Beds & Mattresses

Electrical Work

Ensuite & Bathroom Upgrade

Fire Doors

Flooring

Liverpool

Integrated Projects

Summer Refurbishments

112-Studio PBSA Summer Refurbishment, Liverpool | Simetria

112

Units

140

Fire Doors

7

Weeks

Electrical Work

Ensuite & Bathroom Upgrade

Fire Doors

Flooring

Furnishings

London

Integrated Projects

PBSA Studio Upgrades

42-Studio PBSA Summer Refurbishment, Wembley | Simetria

42

Units

5

Weeks

£350k

Investment

Painting and Decoration

Lighting

Kitchens

Internal Doors

Furniture

London

Integrated Projects

PBSA Studio Upgrades

34-Studio PBSA Summer Refurbishment, Wembley | Simetria

36

Units

5

Weeks

£220k

Investment

Beds & Mattresses

Electrical Work

Fire Doors

Flooring

Furnishings

Contact The Team

Configure your integrated project

Select what applies. We'll show relevant experience and get you talking to the right person

(multiple select is available)
Please select at least one service.
Please enter your name.
Please enter your email or phone.
Select your Fire door option (multiple select is available)
Select your Furniture option (multiple select is available)
Rolling programme
Select your Refurbishments option (multiple select is available)
Refurbishment Options (can click more than one)
Rolling programme
Upload failed. Please retry.
Please accept the Privacy Policy.